Remove all grease, oil, dust, residual curing compound, mould release agent or other contaminant that could impair adhesion of the injection ports. The injection ports should be applied over 6-10mm diameter holes drilled at least 50-75mm into the concrete element. For deeper penetration deeper holes should be considered. Use Master Emaco 2200 to adhere the injection ports over the holes ensuring that the adhesive does not block the drilled holes. Allow the Master Emaco 2200 to cure before injecting .The ports should follow the crack at intervals of500mm or a maximum of 1m centres. Inject from the lowest point or furthest point towards the centre checking for resin coming out of the next hole along. For detailed instructions on crack injection ask you BASF representative for the Master Inject guide to crack injection
Mixing Proportion part kits accurately mixing only what can be used in less than 30 minutes. Thorough lystir Part A, add Part B and blend thoroughly us inga slow speed mixer fitted with a suitable paddle.